Tuesday 30th March, 12pm

 

Join our webinar next week to find out how hybrid power systems offer a sustainable and efficient alternative to using a diesel generator alone on site. Discover how they can help you deliver cost savings, reduce emissions and run silent power to loads when needed, all monitored and controlled by one of the most sophisticated telematics energy management systems available.

 

 

 

 

Presenting the webinar is Energy Solutions’ Commercial Director Mark Penny.

Mark has worked on the integration of hybrid power solutions

with customers including Eurotunnel, Interserve and JCB. 

 

www.energy-solutions.co.uk

With less than 24 hours notice it left contractors the mammoth task of closing down active construction sites as quickly and safely as possible.

One year ago today (March 23), Prime Minister Boris Johnson announced that the UK was to move into a full lockdown as the Covid-19 pandemic swept the nation.

With less than 24 hours notice it left contractors the mammoth task of closing down active construction sites as quickly and safely as possible.

Despite pleas for construction workers to be given “essential worker” status, the government ordered the shutdown of most sites leading to delays and cost overruns on projects big and small.

Lack of certainty over when the crisis would end made the planning and implementation of shutdowns all the more complex. Achieving safe closure with minimal notice only added to that challenge.

Most sites remained closed until June. After which Covid-related measures had to be implemented on site, such as social distancing, one-way walking systems and extra cleaning processes.

These extra measures both took time to implement and have also added time to some construction timelines.

Future planned projects have also suffered with Crossrail 2 and the Bakerloo Line Extension both mothballed as TfL coffers ran dry.

Most of the UK’s biggest infrastructure projects have in one way or another been hit by the impact of Covid restrictions, with Covid blamed for delaying progress at Hinkley Point C, Crossrail, Tideway and the A303 Stonehenge Tunnel.

Hinkley Point C

The cost of Hinkley Point C nuclear power station has risen by around £500M and its start date pushed back to June 2026 due to delays arising from the Covid-19 pandemic.

In January, EDF said it expected the Somerset project to cost up to £23bn compared with a 2019 estimate of a £22.5bn maximum.

The start of electricity generation from Unit One of the power station had been scheduled for the end of 2025, but work postponed last year at the height of the first lockdown has not yet been completed.

In a message to employees, Hinkley Point C managing director Stuart Crooks said: “Ten months after it began, we are still facing the full force of the pandemic.

“Even though experience has allowed us to increase numbers on site during the pandemic from below 2,000 to more than 5,000, social distancing requirements still limit the number of people we can safely have on site at any one time.”

Crooks added that “a longer construction period also adds some cost — as does the reduced efficiency of operating a site for a long period under Covid-19 conditions”.

Crossrail

In August, Crossrail Ltd announced that it will need up to an additional £1.1bn to complete the central section of the London route.

The opening date of the Elizabeth Line has also been pushed back further and is now set for the first half of 2022 – although TfL commissioner Andy Byford has repeatedly called for the line to open at the back end of this year.

It comes after Crossrail’s board thrashed out a new timescale and cost for the project following Covid-19 delays and a downturn in productivity.

The cost increase is on top of the £2.15bn additional funding package which was given to Crossrail after it missed its original opening date of December 2018.

Alongside cost hikes on the Network Rail side of the project, the overall Crossrail scheme is now coming in above £19bn.

As revealed by NCE, the project also saw an increase in slips, trips and falls after sites were reopened as safety briefings switched to protecting against the spread of Covid – this has since been addressed.

Tideway

Covid-19 restrictions have added nine months and a further £233M to the completion date of the Tideway supersewer project, according to a shareholder announcement revealed in August.

Project promoter Bazalgette Tunnel Limited said that the project is now “likely to be completed in the first half of 2025” instead of the anticipated 2024 finish date.

Shareholders were also warned of rising costs with forecasts adding £233M to the previous cost estimates putting the overall cost of the project at £4.133bn.

In an investor report released a month earlier, Tideway revealed its “severe downside” forecast which outlined Covid-related extra costs could result in a cost rise of £900M.

The investor report did warn of a scenario in which the Covid-19 impact could drive up the final cost to £4.1bn. The report also outlined a second “worst-case” scenario that could see costs of the remaining work spiral by 24%, which translates to a total cost of £4.3bn.

Stonehenge Tunnel

The A303 Stonehenge Tunnel scheme was finally given the go-ahead by transport secretary Grant Shapps in November.

Shapps granted a Development Consent Order (DCO) for the scheme, despite The Planning Inspectorate concluding that the scheme would have “adverse effects” for local roads, would cut off local communities and was a risk to the natural and historical landscape.

The government’s decision on the DCO application had already been delayed twice. The first delay was due to the impact of Covid-19 and the more recent delay was due to the discovery of “archaeological finds”.

Documents released by the Planning Inspectorate show that the delay on the decision means that the opening date for the Stonehenge Tunnel will be pushed back by a year.

Tracked changes in the Highways England documents show that the impact of the planning delays will push the start date for preliminary work on the Amesbury to Berwick Down scheme back from summer 2020 to spring 2021.

The main work will be also delayed by a year to October 2021 with the completion date also moving back by a year to 2027.

Heathrow Airport Expansion

The airport industry has felt the impact of Covid harder than most. Passenger numbers have fallen off a cliff and major expansion programmes have come grinding to a halt, with London City Airport bosses pausing its own expansion in the midst of construction.

At Heathrow, things are just as dire. Heathrow handled 22.1M passenger in 2020, compared with 80.9M in 2019 but it wasn’t just passenger flights that have been affected by the pandemic as cargo volumes passing through Heathrow also fell by 28%.

Work on Heathrow’s planned third runway had stopped prior to Covid due to a High Court judge ruling that the government failed to take into account climate change goals when giving the project the go-ahead.

That ruling has since been overturned in the Supreme Court. However, the financial situation – and continued uncertainty around passenger numbers – means the expansion programme remains on ice for the time being.

Despite this, Heathrow bosses continue to push the need for expansion and will no doubt revisit it once travel bans are lifted.

High Speed 2

In the midst of lockdown version one, the government gave the industry a massive boost by providing notice to proceed for phase one of HS2 between London and the Midlands.

It effectively paved the way for main construction, with progress of HS2 ramping up at the back end of last year.

Tunnellers are now preparing to launch at the foot of the Chilterns and work is underway on the UK’s longest rail viaduct.

The second phase of the project, to take the line north to Crewe, has also been buoyed after receiving Royal Assent earlier this year.

What happens beyond Crewe remains to be seen with the government’s much-anticipated Integrated Rail Plan now delayed until after the local elections in May.

While the construction timeline for HS2 remains largely unchanged by Covid-19 for the time being, the project’s chief executive Mark Thurston admitted in May last year that HS2 stations and trains may be redesigned for post Covid-19 world.

The project has also been beset with construction complaints as work has ramped up. As revealed last week, more than 1,400 construction-related complaints were received last year, many of which relate to breaches of Covid-19 restrictions.

Summary

  • March 2020: Contractors strive to shut sites quickly and safely
  • March 2020: Mothballing of sites hits major projects including HS2
  • May 2020: HS2 stations and trains may be redesigned for post Covid-19 world
  • May 2020: Stonehenge Tunnel planning decision delay pushes opening back to 2027
  • August 2020: Covid-19 pushes Tideway costs up by £233M as nine month delay announced
  • August 2020: Crossrail needs another £1.1bn as opening date pushed back to 2022
  • November 2020: Stonehenge Tunnel gets planning green light
  • January 2021: Hinkley Point C suffers another £500M cost rise and delay

Source: New Civil Engineer

Romal Capital has committed £100m for a mixed-use development in Liverpool’s Central Docks area.

In its planning application to Liverpool City Council, the property developer will progress the work it completed on Quay Central and Park Central, having built 237 residential apartments and commercial tenancies, which were delivered last year.

The new £100m scheme includes 330 sustainable ‘smart’ homes, retail space, as well as other amenities and public areas.

It proposes a mix of one-, two- and three-bedroom apartments designed to attract occupiers ranging from professionals to young families.

To reduce net carbon emissions, each home will feature power usage monitoring and solar panels installed in common areas.

Romal Capital aims to encourage the use of electric cars, with up to 20 EV charging stations to cater for the government’s zero-emission vehicle initiative.

It is expected that the commercial units will attract a range of occupiers, including hairdressers, beauty salons, delicatessens with indoor and outdoor dining, bike rental and kayak stores.

The proposed new public spaces include an active waterfront, marina floating pontoon, a suspended six-metre-wide cathedral-style bridge bordering the river canal for pedestrian and bike access, rooftop gardens and leisure space for al fresco dining.

A new cultural square would be used for market days, music and entertainment.

The spaces are designed to lend themselves to hybrid living, working and learning environments in a post Covid-19 world.

Greg Malouf, CEO at Romal Capital, said: “We are very excited about this scheme and it’s potential to transform this barren brownfield land into a thriving new waterfront neighbourhood.

“The combination of new smart homes, carefully selected retail and leisure outlets, and huge investment in new public realm will deliver a high quality lifestyle for its residents.

“New, high quality homes on this brownfield site means new jobs, greater investment and ultimately more people to enjoy this waterfront location.

“We hope this scheme acts as both a major catalyst and benchmark for future development within the area.”

Romal Capital will be working with principal landowner Peel L&P in developing the Liverpool Waters regeneration zone.

 

Source: Development Finance Today

 

 

It has now been 122 days since Highways England pulled its Lower Thames Crossing plans, meaning Highways England has missed the target date for resubmission set by the project’s boss.

The planning application was withdrawn in November following feedback from The Planning Inspectorate that it was poised to reject the plans.

Lower Thames Crossing executive director Matt Palmer said that he expected the plans to be resubmitted within 90 to 120 days of the original application being withdrawn.

He added that he expected the development consent order (DCO) application to be resubmitted early in the New Year, adding that this is a “speed bump, not a complete stop”.

“It doesn’t feel like it will take a long time to turn around. If you look at other [DCO] applications that have been withdrawn they tend to be resubmitted in 90 to 120 days and I think we are looking at that sort of timeframe,” Palmer said.

“The application itself is 42,000 pages. We have taken all the lessons learnt from other, successful Highways England projects and applied those to the DCO.

“[The Planning Inspectorate] obviously wants more information so we have taken on board what they have said and we are confident we can provide that.

“The difficulty with a project of this scale and this significance is that there is no magic bar to jump over – it is about finding where that bar is and that’s what we’ve got to do now.”

The Lower Thames Crossing project will connect Essex with Kent to the east of London, helping to alleviate congestion on the Dartford Crossing.

The Planning Inspectorate’s concerns relate to construction plans and the predicted ecological and environmental impact of the scheme.

In a community update released last week, Highways England head of communications for its complex infrastructure programme Sarah Walker confirmed that the team is “busy” collecting the information required by the Planning Inspectorate.

She added: “The Planning Inspectorate has asked us to provide some more information on some technical elements of our application and we are busy bring this information together, but we also see this as a great opportunity to strengthen our application as we continue to work with key stakeholders to make the Lower Thames Crossing the best it can possibly be.”

A Highways England spokesperson added: “We are continuing to work with the Planning Inspectorate and are carrying out extensive engagement with our neighbouring local authorities to address their feedback, and take the opportunity to strengthen our application.

“We appreciate that there are millions of people every year who are frustrated by congestion on the Dartford Crossing, and who are looking forward to the opportunities that come with building a scheme on this scale, and we can reassure you that we will be resubmitting our revised, stronger application as soon as possible.”

Since pulling the application Highways England has awarded Jacobs a £162.5M integration partner contract for work on the Lower Thames Crossing.

Jacobs will act as a catalyst for collaboration between Highways England and the project’s three main works contracts.

Palmer previously announced the start of procurement on the design and build contract for the project’s tunnels at New Civil Engineer’s Future of Transport conference at the start of November.

The main works contractor will be responsible for boring the two 4.2km long tunnels beneath the River Thames; construction of portal buildings and approach roads; and fit out of the tunnel systems with systems including ventilation and lighting.

The tunnels will be the largest diameter tunnels in Europe and the third largest in the world with a diameter of 16m. They will also be the longest road tunnels in the UK.

Their size is determined by the need for each bore to cater for three lanes of traffic travelling at up to 70mph. The contract is expected to be awarded in 2022.

The tunnels and approaches contract is the first of the three main works contracts to be procured for the scheme, with the Roads North and the A2 M2 contracts expected to be announced early in 2021.

When speaking in November, Palmer added that the procurement timeline is likely to be pushed back a month or two because of the DCO setback but added that it “will have no impact on those bidding [for the contracts]”.

It is understood that the remaining contracts will be put out to tender within the next month or so.

Ground investigation work has been ongoing at the site since 2017. The third phase of ground investigation work finished this summer, led by the Perfect Circle JV comprising Pick Everard, Gleeds and Aecom.

In total, more than £100M has been spent on ground investigations due to the chalky conditions in that part of the Thames.

 

Source: New Civil Engineer

 

Irish Sea link ‘unworkable in isolation’

An Irish Sea link connecting Northern Ireland with Great Britain “is unworkable in isolation”, according to transport thinktank Greengauge21.

In response to Sir Peter Hendy’s interim report on Union connectivity – which recommends a full feasibility study of a fixed Irish Sea link – Greengauge21 has called for a raft of transport upgrades either side of the Irish Sea in order to facilitate a bridge or tunnel.

Among its suggestions, Greengauge21 has called for a new electrified railway between Stranraer and Carlisle as well as “fast rail onward connections” to the rest of the country.

“Just as was found when the Channel Tunnel (Eurotunnel) was built, a cross-channel tunnel is unworkable in isolation,” Greengauge21’s report states.

“Kent needed the completion of the M2 and M20 motorways and the construction of the channel tunnel rail link (HS1) for it to work properly.”

However, instead of building new motorways to the tunnel, Greengauge21 recommends better rail connections – to support its previous proposal of a rail tunnel in the Irish Sea. It claims that by building fast rail links to a terminal would remove the need for a 160km new motorway across Dumfries and Galloway.

“A new electrified railway line is needed (between Stranraer and Carlisle) to feed a tunnelled rail link across the Irish Sea.

“As well as through freight trains and fast passenger services, this could be used to provide an extended Euro-shuttle style operation, allowing HGVs and cars to transit under the Irish Sea and continue across south west Scotland.

“A terminal would be provided where the rail line meets the M6/A74(M). South West Scotland could be similarly spared the ravages of increased traffic levels.”

It adds: “Its virtue is that it takes away the need for a 100-mile stretch of motorway across Dumfries & Galloway and opens the possibility of both faster transit times and significant carbon reduction.”

Hendy will submit his final Union Connectivity review in the summer. Alongside a feasibility study for the Irish Sea link, Hendy will also look at ways of improving transport connections between England, Scotland and Wales.

As well as building a new railway to the proposed tunnel, Greengauge21 suggests upgrading existing rail lines to provide faster journeys from London to Belfast.

“If the fixed link is also to provide an attractive alternative to flying between Northern Ireland and English & Scottish airports, then fast rail onward connections are needed,” the report states.

“One aim would be a sub-4 hour rail journey time between London and Belfast. This is only achievable if work proceeds to speed up the Crewe-Carlisle section of the West Coast Main Line through northern England, which might well happen in pursuit of 3 hour journey times London-Glasgow/Edinburgh.

“So this too is a pre-requisite for success, just like the cross-Galloway rail line.”

Greengauge21’s original submission to the Union Connectivity review also calls for upgrades to existing Anglo-Scottish rail lines, electrifying the Holyhead-Chester-Crewe railway line and completion of the Borders Railway.

Source: New Civil Engineer

WHAT ARE THE FIRE IMPLICATIONS WHEN A BUILDING OWNER PLANS TO ADD THREE EXTRA STORIES TO A TOWER BLOCK?

Iain Cox, Chair of the Business Sprinkler Alliance

 

A property owner has submitted a planning application to add three additional stories to a North London residential tower block to help fund the removal of unsafe ACM cladding on the lower 14 floors. Whilst the concept might be  sound on paper, has the design considered the fire safety aspect and how to keep people safe in a building that will be changed?

The owner of Premier House in Edgeware, North London, is planning to add three additional stories and a rooftop garden to the building to partially fund the remediation work on the rest of the building. This planned alteration also brings into sharp focus the 2020 change to Permitted Development Rights (PDR) allowing building owners to add up to two storeys on top of existing detached and purpose-built blocks of flats through a fast-track process. In either case, it is critical to ask the question, how has the risk changed by adding these floors?

 Upward extensions such as the one proposed at Premier House need to be carried out after careful consideration and assessment of the existing building and its fire strategy. Which sort of evacuation plans are in place for the current building? How many extra people will be residents in the altered building? Will the staircases and door widths accommodate these additional people and provide access to firefighters? Which material is the new extension going to be made of?  Will it alter the fire load materially? The change needs to be considered holistically not on the addition alone.

There is a tendency to think about the structure, aesthetics and thermal efficiency of the new sections of the building when undertaking such alterations. What is needed is to reconsider the fire safety of the building from the ground upwards. Renovations and changes such as these are often intended to make the building better for its tenants.  Unfortunately the law of unintended consequences often means that these intentions are not realised.

Another consideration is the new 11-metre storey height sprinkler threshold that came into force last November. This will be an interesting case to follow as this change will have implications for the overall building. Regardless of this change, from a fire safety perspective sprinklers make a lot of sense and are a key component in the long-term strategy of any building. If considered early in the design process, they can be included and implemented whilst balancing costs. Developers need to have an open mind to other fire safety solutions, particularly sprinklers, and think about the best solutions to employ for such a change considering the building as a whole

Early consideration of automatic sprinkler systems in the design process, opens up a number of significant design opportunities which could provide solutions, to the challenges such projects will inevitably face.  This will only happen when the fire strategy for the whole building is considered at the start of a project.  We must stop thinking of fire safety as an ‘add on’.

 

For more information about the BSA visit the www.business-sprinkler-alliance.org

 

 

 

Combilift is the largest global manufacturer of multi-directional forklifts and an acknowledged leader in long load handling solutions. More than 50,000 units have been sold in over 85 countries since Combilift was established in 1998. Innovation, Flexibility and Service is the ethos on which Combilift’s success is built and has seen us become the world’s fastest-growing forklift manufacturer, exporting to more than 85 countries and with more than 52,000 trucks in use worldwide. No other manufacturer in the world can deliver the same level of customisation and adaptability, or cater so effectively to the diverse needs of every individual customer, whether their enterprise is large or small.

 

COMBILIFT

Annahagh,  Monaghan, Co. Monaghan H18 VP65 Ireland

Phone: +353 47 80500

web: combilift.com

The Church could use its vast landholdings to transform the construction industry for the better as well as helping ease the housing crisis, the chair of the C of E’s housing commission told Building Design.

By taking a long-term view of its assets and requiring development partners including architects and contractors to sign up to the five values in the commission’s report, it could become a much more influential player in housing development, said Charlie Arbuthnot. The specialist in social housing financing led the Commission on Housing, Church and Community whose report, Coming Home, was launched last month.

It sets out a vision of housing that is sustainable, safe, stable, sociable and satisfying – and includes a series of detailed recommendations for government and society as well as for the Church itself.

If the Church insisted on working only with partners that shared these values, said Arbuthnot, “we start setting a benchmark for a very different ethos. That’s exciting. As soon as that becomes normative we have transformed an industry”.

He gives the example of a housebuilder with a bad reputation. “They build stuff and in six months when things start going wrong they don’t answer the phones,” he said. “That doesn’t fit with safe, stable or satisfying housing. If that housebuilder is pitching for a piece of work we’d say, ‘Your history suggests our five values aren’t important to you. I don’t mind if you do it cheaper than the others – our five values are more important.”

He admits the values are impossible to police but says they make a “healthy baseline” and if a contractor commits but doesn’t deliver, “the next contract becomes harder to win”. He also points to the much more enforceable Stewardship Kitemark which is currently in draft form.

It would allow a congregation with no experience of building projects to go to their local authority and say, “We have this land which could help address local housing need but we don’t want to release it unless what is built meets the five values. Can we talk about how we steward this well for the common good?”

The Church has nearly 200,000 acres of land, about half of it owned by a patchwork of parishes and dioceses and the rest owned by the Church Commissioners, the Church’s investment arm. They have built 3,820 homes in the last five years, just 21% of them affordable.

The Church Commissioners argue their hands are tied by charity law, but moves are now afoot to change the Church’s internal regulations which could free them to sell land below market price. Arbuthnot is hopeful this could be completed this year and he and his fellow commissioners are encouraging the Church to aim for a far more ambitious proportion of affordable housing.

They would also like to see the Church choosing not to sell its land but remain long-term stewards, reinvesting rents in further developments. Arbuthnot believes this would result in projects being better designed and built.

“We are absolutely saying that. We want to position the Church to build community really well – and I don’t do that if I sell my field to someone who builds the maximum number of units on it for the cheapest price,” he said. “If instead I choose to steward it, I’ll want to reflect Christ in the way I run it.”

The report also listed demands for the government, urging it to create a 20-year, cross-party strategy to transform housing and solve issues from affordability to dangerous cladding. It should include a specific target for the number of homes which are truly affordable, and seek to improve the quality and environmental sustainability of existing housing stock.

The Archbishop of Canterbury, who commissioned the report, said it came as the country faced a “Beveridge moment”, linking the current pandemic and the landmark 1942 report that led to the creation of the NHS and benefits system.

Speaking at a launch event for Coming Home, Helen Barnard, director of the anti-poverty think tank Joseph Rowntree Foundation, said: “A lot of people can get behind this in the sector and more broadly and this is the moment to do it. The importance of a safe, warm home you can afford has been brought home to us in an incredible way and we need that economic stimulus.”

She added: “There’s a focus in the report on listening to tenants but we should go further and put co-design – working with people to design solutions – at the heart of everything we do.”

 

Source: Building Design

 

Cladding and other fire safety issues for flats in high-rise buildings could affect roughly 1.5 million flat owners in the UK, many of which will face significant hurdles when trying to sell these flats or obtain a mortgage on them. Insurance premiums may also increase for flat owners, and some will have to pay for safety patrols until the safety issues are resolved.

Analysis from the financial consultant, DBRS Morning Star, based on a sample of 670,000 mortgage loans, found that:

Hotspots for flats are London (28.5%), Glasgow (3.7%), and Edinburgh (3.2%). East London has the most flats, accounting for nearly 7.5% of all UK-wide flats.

House prices would need to decline by more than 20% of their current value for a meaningful number of mortgage borrowers to end up in negative equity.

Fire safety repair bills (even after accounting for differences in labour costs) may not be proportional to the property value. This means that borrowers in the northern UK where property values are cheaper could have repair bills which, relative to their property value, are higher than in London.

Ketan Thaker, head of European RMBS and Covered Bonds, comments: “Borrowers are likely to face higher mortgage costs because of an increase in their mortgage loan-to-value ratios, either as result of reduced flat values or additional debt undertaken to fund repairs.

“DBRS Morningstar’s analysis shows that, assuming that borrowers can remortgage, they may still face higher monthly payments in most cases. Furthermore, the impact could be much more severe for borrowers if they cannot get a new mortgage and have to move onto the lender’s standard variable rates, which tend to be higher.”

Property management operator MetroPM has welcomed a new valuation process issued by the Royal Institution of Chartered Surveyors (RICS) over valuing high-rise properties with cladding.

The industry-wide guidance is titled ‘Valuation of properties in multi-storey, multi-occupancy residential buildings with cladding’, and follows consultation with valuers, leaseholders, lenders, fire safety experts and government.

Matthew Arnold, managing director of MetroPM, explains that the paper had been agreed with the Building Societies Association and UK Finance and will clarify which types of properties will or will not require additional inspections due to concerns about fire safety.

He says: “We welcome this guidance which will help to create clarity and consistency about when a valuer is not required to request further investigation of cladding before valuing a property in a building of multiple occupation.”

“Importantly, it makes it clear that where a valuer or lender can establish that the building owner has met the advice in the consolidated advice note, an EWS1 form should not be required. An EWS1 form would also not be required for a building that is over 18 metres that has a valid building control certificate in place.”

Arnold mentions that MetroPM, which has offices in Birmingham and Cheltenham, is currently dealing with blocks where cladding needs to be removed and so would find the advice ‘extremely useful’.

The guidance details that an EWS1 form will only be required for the following:

Buildings over six storeys with cladding or curtain wall glazing, or vertically stacked balconies made from or connected by combustible materials (such as timber).

Buildings of five or six storeys where there is significant cladding (covering approximately a quarter of the building or more), or there are ACM, MCM or HPL panels on the building, or there are vertically stacked balconies made from or connected by combustible materials.

Buildings of four storeys or less, if there are ACM, MCM or HPL panels on the building.

Arnold adds: “This guidance details exactly when an EWS1 form will be required for valuations, and this will help to simplify the process, enabling more people to buy and sell homes and re-mortgage in high-rise buildings.”

Scottish cladding crisis event calls for transparency for residents

Edinburgh legal firm Watermans Legal is set to address the continued confusion surrounding Scotland’s cladding crisis with a virtual event for residents.

This comes as demand grows for the Scottish Government to allocate funds to homeowners trapped in their unsellable homes due to combustible cladding.

A £100 million pot of funding was made available to the Scottish Government last year to help tackle the crisis, with mounting pressure on the Scottish Housing Minister, Kevin Stewart, to put an action plan into place to use the funds.

The virtual event – bringing together leading experts from Watermans Legal, Fire Risk Assessment (Scotland) Ltd, J&E Shepherd Chartered Surveyors and Residential Surveyor and M&W Mortgages – will address how cladding issues can affect selling, buying and the mortgaging of properties.

The importance of obtaining and instructing an External Wall Fire Risk Review (EWS1 form), which confirms that a building does not pose a fire risk, will also form a key part of the event’s agenda.

Shawn Wood, a solicitor at Watermans Legal who will be speaking at the event, comments: “The topic of cladding is so closely aligned with England. There’s not nearly as much focus on how it affects Scottish residents.”

“We’re receiving a growing number of calls from people with concerns about their properties and the incurring costs which is why we felt it was necessary to host this event. It’s an opportunity to gather Scotland’s cladding experts and share our knowledge with the public.”

Many people in Scotland who are affected by the cladding crisis have been left confused, with no helpful responses despite huge company profits from builders and the construction industry.

Wood says residents have inherited these problems through no fault of their own.

“Many people are feeling trapped as their homes are effectively worthless if a Home Report returns ‘category threes’ for their external main walls,” he adds. “Obtaining an External Wall Fire Risk Review form, which demonstrates to a buyer that there isn’t a fire risk, can also be timely and expensive due to a shortage of professionals with the necessary qualifications to carry out these specialist reports.”

“If all homeowners were to fix the problem of combustible cladding it could cost tens of thousands of pounds per property which leave many concerned that they will be left to foot the bill if their building is found to have combustible cladding. With the Government’s plan to support Scotland still to be announced, we want to offer any advice that we can to help alleviate people’s fears.”

The Cladding Crisis in Scotland online event takes place on Thursday March 18 from 6-8pm. Interested parties can sign up for free here.

 

Source: Property Investor Today

To ensure the UK government’s commitment to achieving Net Zero greenhouse gas emissions by 2050 is on track, the construction industry will require the equivalent of 350,000 new roles to be created by 2028.

These will need to be found through a mix of new skilled jobs, increased efficiencies in existing roles, and innovation in how the industry decarbonises the built environment. That’s the key finding of Building Skills for Net Zero, published by the Construction Industry Training Board (CITB) today (15 March).

UK construction contributes approximately 40% of the UK’s emissions according to the UK Green Building Council (UKGBC) and reducing this to Net Zero represents a huge challenge. Yet the move to cleaner, greener construction presents big opportunities to make the industry more attractive to new recruits and upskill the existing workforce.

A critical element of achieving Net Zero will be reducing carbon emissions from existing buildings. Across the UK 80% of buildings in use in 2050 have already been built and these could represent 95% of future built environment emissions. Reducing emissions to Net Zero will require retrofit work on up to 27 million domestic and 2 million non-domestic buildings.

CITB has modelled the skills profile of the workforce needed to deliver Net Zero using data from the Climate Change Committee (CCC). This shows that by 2028, additional decarbonisation work will have created the demand for 86,000 construction project managers, 33,000 building envelope specialists and 59,000 plumbers and HVAC specialists.

This opportunity comes alongside the COVID-19 pandemic and an expected rise in unemployed workers coming from other sectors. This is a perfect time for the construction to position itself as a career destination of choice for people who really want to make a difference.

CITB’s research shows that reducing built environment emissions to Net Zero can be achieved if there is an industry-wide investment in skills, far-reaching skills policy reform and an unprecedented recruitment drive. The challenge is great, but so are the rewards, giving thousands of people new career opportunities as we emerge from a time of national crisis.

Chris Carr, Managing Director of Carr & Carr Builders, and Federation of Master Builders Board Member, said:

“The skills challenge around Net Zero is huge and this research shows how it can be tackled. A big part of it will be upskilling the current workforce so that they understand what sustainable building is all about. I welcome this report and the Construction Leadership Council’s National Retrofit Strategy which show how, if we work together as an industry, we can make construction greener while seizing opportunities for growth.”


Thousands of new construction jobs needed for Wales to achieve net zero emissions target

 The construction industry will need to create 12,000 jobs by 2028 if the Welsh Government’s target of net zero emissions is to be achieved by 2050.

According to a report from the Construction Industry Training Board (CITB) these jobs across Wales will need to be found through a mix of new skilled jobs, increased efficiencies in existing roles and innovation in how the industry decarbonises the built environment.

CITB strategic partnership director for Wales, Mark Bodger, said: “Net zero presents a huge challenge for construction, but an even greater opportunity to create a more productive industry that’s also a more attractive career option.

“We can get there by being clear on the key skills we’ll need, making sure we have the right courses and qualifications to deliver them and getting on with investing in them. Industry is already delivering what is needed, but it needs to happen at scale. The training sector must act now as employers’ needs will change fast. A joined up approach to skills across the built environment is key.

“Welsh Government also has a key role in specifying what it wants and creating the pipeline of demand that will give industry the confidence to invest in the skills we need and for providers to invest in the courses we need to deliver these skills.”

Deputy Minister for Economy, Lee Waters, said: “Getting serious about decarbonisation is not just an environmental imperative, it’s an economic opportunity. We’ve got to seize this opportunity to create a new generation of jobs that are sustainable in every sense of the word.

“We can only do it industry, local supply chains, academics and governments all working together innovatively to focus on the practicalities, and then drive forward the implementation to build the workforce we want to see in the future.”

 

Source: FE News and Business Live